November 12 2025

Project Mobilization

November 12 → December 04 2025

Dyke Pathway Closed between 72 Street and 88 Street

November 17 2025

Ditch Widening Starts

March 02 2026

Pump Station Construction Starts

August 24 2026

Forcemain Construction Starts

November 02 2026

Outflow Structure Construction Starts

March 01 2027

Project Ends