Ferry Road Boat Launch

Share Ferry Road Boat Launch on Facebook Share Ferry Road Boat Launch on Twitter Share Ferry Road Boat Launch on Linkedin Email Ferry Road Boat Launch link

Update

Works to replace the boat launch will be occurring during overnight periods between November 20, 2024, and January 15, 2025. Please see the proposed working schedule here.

Overview

The City of Delta is working to replace the two lane boat launch located at Ferry Road in Ladner. The replacement boat launch will have improved functional use outside of high tide conditions.

Removal and construction of the new boat launch will take place between October 28, 2024 and February 15, 2025, to limit impact to the local fish habitat and to minimize disruption during traditional peak boating season.

Works involved in the project include:

  • Removal of existing boat ramp and associated features;
  • Installation a larger boat ramp and rip-rap protection, resulting in new, expanded footprints of 12m2 and 130m2 , respectively; and,
  • Dredging of approximately 685m3 of sediment from the area approaching the boat ramp;
  • Extension of the float to increase boat capacity.

Design

Fig. 1 Existing Boat Launch and Proposed Plan Overlay

Fig. 2 Dredging Area


Update

Works to replace the boat launch will be occurring during overnight periods between November 20, 2024, and January 15, 2025. Please see the proposed working schedule here.

Overview

The City of Delta is working to replace the two lane boat launch located at Ferry Road in Ladner. The replacement boat launch will have improved functional use outside of high tide conditions.

Removal and construction of the new boat launch will take place between October 28, 2024 and February 15, 2025, to limit impact to the local fish habitat and to minimize disruption during traditional peak boating season.

Works involved in the project include:

  • Removal of existing boat ramp and associated features;
  • Installation a larger boat ramp and rip-rap protection, resulting in new, expanded footprints of 12m2 and 130m2 , respectively; and,
  • Dredging of approximately 685m3 of sediment from the area approaching the boat ramp;
  • Extension of the float to increase boat capacity.